Ok went back through my code book and can find no issues with 1 circuit (the well pump) going to the other building. This can have power from both the utility and (with a properly installed gen and transfer switch) the gen as well.
NEC 2014 225.xx and 250.xx address the “separate building” and provide some exemptions for a single circuit.
NEC 2014 also addresses gens but the discussion is around proper grounding, neutrals and ensuring utility and gen power is isolated from each other- proper transfer switch.
NEC 2014
445.xx
702.xx
As mentioned early on in this thread by LueNY a properly labeled and installed single circuit from the new building back to the old building to power the well will be the easiest way to provide utility and gen power to that circuit.