Good morning guys,
Eddie and Knight,
Sorry if my first posting was unclear.
This project was started in April of this year, 2007....both the homesite clearing for the log home and the barn pad. They were BOTH to be completed by May of this year 2007.
That was when the GC wanted to start, assuming the bank loan and everything else was in order. So what I am doing is bringing you up to date from April of this year 2007 to present. That means the barn pad and homesite will only sit for one ... a couple of months, max.
To clear things up further, instead of starting construction in May as planned, he actually started this June 2007. So that is only a month ago from today. And yes Knight, the pad is for the barn, not the log home.
But both the barn pad and the clearing/site prep work for the log home had to be done at the same time, since I did not know which one he was going to start on first. I know I'm kinda crummy at explaining myself at times, so I hope that helps.
Anyway, these events took place earlier this Spring and I will get you caught up to the present ... and sorry for misleading you. LOL, you can tell I'm a mold maker and no writer huh? That's why I always put a lot of pictures in the threads.