It's been a while since I updated, but the work has never stopped. We encountered a lot of delays in supplies due to COVID so things didn't progress as fast I wanted this spring/summer, but nothing you can do about that.
Anyways, here are a few things we've been up to:
In April, we were able to get our lower patio under the deck poured:
Then, it was on to top soil (free from our road excavation through the ag field), and seeding:
First, stump removal:
By May, it took off (then subsequently dried up with our drought this summer):
I installed almost 300' of gutter guard:
I put up the deck railing using Radiance Rails from Timbertech, and their glass channel kits. Decided to use glorified Plexi for now, but will switch to tempered glass down the road as budget allows.
I built stairs off the deck, but they still remain unfinished due to a nation wide shortage and backorder on Azek/Timbertech:
And I'm in the process currently of setting a 500 gallon propane tank underground:
So, that's where we are in a cliff notes version. There are lots of other small projects I completed that I didn't document, but I felt I should update the thread since I let it go cold for so long!