Nubota. Again as I mentioned earlier, you should check with your local concrete provider and see if they have ready mix available in a buggy. It holds 1 cu/yard and by my calculations, you need 4.5 yards. The cost should be comparable to mixing it on your own and all you really need to do is pour it. As you know, 1 cu/yd is equivalent to 27 cubic feet: That is a LOT of mixing, anyway you cut it (equivalent to 41 bags of 80lb mix). The amount of time required for this project really just depends upon how fast you can make 5 trips to the concrete supplier to refill. You tow it back, pour directly into forms or into wheelbarrow or into your loader bucket. The buggy also comes with hydraulic dump ram to help with the pour. Frankly, I can't see why anyone would want to mix their own if this option is available.